Cutlass II Solar Power Plant

SOLAR

Cutlass II Solar Power Plant

Fort Bend County, TX
date_range

FNTP January 2023

COD Mid-April 2024

Capacity

272 MWDC

218 MWAC

  

Contract Details
Site Control 30 years plus two 5-year extension options
QSE Tenaska
Permitting Complete
Modules JA Solar (Bifacial)
EPC Bechtel
Inverters Power Electronics
Trackers Array Technologies
Project Milestone Targets ve Date
Site Control Completed
Interconnection Agreement Executed Q1 2021
PPA Executed January 2023
Final Notice to Proceed Executed January 2023
Commercial Operation Date Mid-April 2024

Community Impact

Sabanci Renewables acquired the 272 MWdc Cutlass II solar photovoltaic project in Houston, Texas (ERCOT). The project, located in Fort Bend County, reached COD in May 2024. The acquisition of Cutlass II is a significant step in Sabanci Renewables Inc.'s expansion into the US renewable energy market.

The Cutlass II project seeks to cultivate significant value for the local community, creating jobs, supporting economic growth, and providing environmental advantages. Cutlass II created 300+ jobs during its construction and ten permanent jobs during operation, powering 40,000+ homes, and bringing long-term economic benefits. As a low-carbon energy source, the solar project mitigates air pollution and decreases greenhouse gas emissions as well as conserving water.

Phase I ESA

Cultural Resources Reporting

T&E Species Habitat Assessment

Wetlands Delineation

Sponsored Organizations

Here are some of the specific environmental advantages of solar power plants:

  • They produce zero Scope 1 emissions, which helps to improve air quality and reduce overall greenhouse gas emissions.
  • They require little water usage.
  • They have a long lifespan and can generate electricity for many years.